  • Construction Progress
    March 2016



  • The structural works from level 1 to level 2 of Building C, Building E, and Building F are almost completed. Also the structural work for Building D has reached to level 4, for the ground floor of Building B is on-going. The installation of the services is on-going from the basement.

2-1-16
2-2-16
2-3-16
2-4-16

  • Construction Progress
    February 2016



  • The structural works from ground level to level 1 of Building D, Building E, Building C and Building F are completed. Also the structural work of Building D has reached to level 3. The installation of the services is ongoing from the basement.

1-1-16
1-2-16
1-3-16
1-4-16
1-5-16

  • Construction Progress
    January 2016



  • The structural works from ground level to level 1 of Building D, Building E, Building C and Building F are ongoing. Also the structural work from level 1 to level 2 of Building D is ongoing.

12-1
12-5
12-3
12-4
12-2

  • Construction Progress
    December 2015



  • The structural works above the ground floor of Building E started, while Building D started the floor slab structure of Level 1.

11-4
11-1
11-2
11-3

  • Construction Progress
    November 2015



  • The structural work above the ground floor of Building D started, block works started at the same time.

10-1-15
10-2-15
10-3-15
10-4-15

  • Construction Progress
    October 2015



  • All the structural works below ground level are finished, and remedy works of the basement is underway. Also the back fill work is carrying on.

9.1
9.2
9.3
9.4

  • Construction Progress
    September 2015



  • All the works below ground level are finished, and the ground floor slab has been finished as well.

9-1
9-2
9-3
9-4

  • Construction Progress
    August 2015



  • All the major construction work below ground level are finished, which is including Basement level 2, Basement level one and the flooring of the ground floor.

7.1
7.2
7.3
7.4

  • Construction Progress
    July 2015



  • Level B02 (Basement 02) of all stage 1 development were finished. Level B01 (Basement 01) of Building D and E were finished, Building C and B are about to finish. Building A and the rest of the area are showing a good progress.

6.1
6.2
6.3
6.4

  • Construction Progress
    June 2015



  • Structures of Building D,C and B of basement 2 were all finished; structures of Building D,C and B of  basement 1 are ongoing and showed very good progress. Floor slabs of Building E and F were finished. Building A slab work is ongoing. Also, structures of Building E of  basement 1  is ongoing.