  • Construction Progress
    January 2017



  • For external façade, Building A and B continuing with roof framing and ply, and started wall framing. Building C and D continuing with designer series. Building E and F roof membrane done, started installing aluminum joinery. For internal fit out, Building A and B continuing with steel stud and service first fix on level 6. Building C started gib stopping in bathrooms,  and gib fixing in apartments. Building D started painting in apartment, and soundboard、waterproofing to bathrooms, continuing with gib fixing in apartments. Building E and F completed steel stud and services first fix.

img_3177
img_3169
img_3168
img_3171
img_3170
img_3172
img_3176

  • Construction Progress
    December 2016



  • For internal fitout works, building A and B working on steel stud and all services first fix, building C、D、E、F are completed steel stud and most of services first fix. For external façade, building D is continue with closing in building with aluminum joinery installation and glazing, as well as the designer series cladding, building C is continue with RAB and aluminum joinery installation. Other buildings are ready to start with designer series and glazing installation.

rosegarden
img_2835
img_2834
img_2836
img_2841
img_2842
rosegarden_o

  • Construction Progress
    November 2016



  • The structural works for all buildings are completed, and roof works are in progress to make the buildings watertight. The internal fitouts、services first fix、gib fixing、RAB、aluminum joinery installation for each building are continue in progress.

img_2575
img_2577
img_2578
img_2579
img_2580
img_2582

  • Construction Progress
    October 2016



  • The structural works for all buildings have reached the top floor, and roof works are in progress to make the buildings watertight. The internal fit out works and wall framing for each building are continue in progress.

img_2208
img_2222
img_2215
img_2221
img_2216
img_2214
img_2219

  • Construction Progress
    September 2016



  • The structural works for Building A & Building B are working on level 5, Building E & Building F have reached the top floor. Building C & Building D roof structure are installed and roof works are in progress to make the buildings watertight, which will allow the internal fit out works to commence. The installation of internal wall framing for each building and lift installation are continue in progress.

DCIM100MEDIADJI_0116.JPG
IMG_1848
IMG_1851
IMG_1850
IMG_1856
IMG_1858

  • Construction Progress
    August 2016



  • The structural works for Building A level 3 and Building B level 4 are completed. Building C、Building E and Building F have reached to level 5、level 6 and level 6 respectively. Building D level 6 work on roof has almost completed. The installation of the services have already completed from the Basements and Podiums, and the installation of internal wall framing for each building are in progress.

IMG_1597
IMG_1595
IMG_1598
IMG_1599
IMG_1602
IMG_1604
DCIM100MEDIADJI_0109.JPG

  • Construction Progress
    July 2016



  • The structural works for Building A level 2 and Building B level 3 are completed, Building C、Building E and Building F have reached to level 5、level 5 and level 6 respectively, Building D level 6 is almost completed and work on roof has started. The installation of internal wall framing for each building are in progress.

0701_2
IMG_0496
IMG_0484
IMG_0480
IMG_0481
IMG_0492

  • Construction Progress
    June 2016



  • The structural works for Building A ground floor and Building B level 2 are completed, Building C、Building E and Building F have reached to level 5、level 5 and level 4 respectively, Building D level 6 is almost completed and work on roof has started. The installation of the services are almost completed from the Basements and Podiums.

full
a - Copy
c
d
e
f
p
base
base2

  • Construction Progress
    May 2016



  • The structural works for Building A ground floor and Building B level 1 are ongoing, Building C level 3 has been completed, Building D、Building E  and Building F have reached to level 6、Level 3 and level 4 respectively. The installation of the services are almost completed from the Basements and Podiums.

0506_1
20160506 (11)
c
d
e
f
inside
20160506 (10)

  • Construction Progress
    April 2016



  • The structural works for Building A has started from the ground floor, for Building B ground floor is on-going, for Level 2 of Building C, Building E, and Building F, and level 4 of Building D are almost completed. The installation of the services is on-going from the basement.