  • Construction Progress
    November 2017



  • For external façade: Building A dismantled metal cladding scaffolding and working on podium level lobby roof; Building B working on bottom drop of metal cladding; Building E completed bottom drop of metal cladding; Building F completed podium balcony balustrades and working on bottom drop of metal cladding. For internal fit out: Building A completed installing kitchens and trim, continuing tiling kitchens and work in bathrooms, painting to level 6 apartments, started carpet laying; Building B started inspections in apartments; Building C and Building D arranged final inspections for purchaser and started remedy the defects; Building E and Building F completed inspections in apartments; For road & landscaping: completed streetlight cabling, working on streetlights and footpaths at ducts junctions/bends.

IMG_4665
IMG_4664
IMG_4666
IMG_4668
IMG_4669
IMG_4671
IMG_4670

  • Construction Progress
    October 2017



  • For external façade: Building A working on fins; Building B dismantled all scaffold; Building E continuing building podium balconies and completed metal cladding on east elevation; Building F completed metal cladding and dismantled scaffold on west & east elevations. For internal fit out: Building A started installing kitchens, continuing with trim and painting to apartments, and working in bathrooms; Building B started installing appliances, continuing carpet and second fix services to apartments, and working in hallways; Building C and Building D taking CCC inspections with Council、NZRG and Context architects; Building E and Building F continuing with initial cleans, tiling in lobbies, and ready for inspections in apartments; For road & landscaping: Electrix have started streetlight cabling, waiting on road marking & signage details and Munro Lane design.

1016_1
1016_4
1016_5
1016_8
1016_7
1016_9
20863361_1604711549566978_7235210522465351688_o

  • Construction Progress
    September 2017



  • For external façade: Building A completing last of designer series; Building B installing louver sunshades and working on metal cladding; Building C continuing metal cladding and plastering on podium lobby now base flashings sorted; Building D completing last bits of plaster and installing replacement canopy glass; Building E continuing with metal cladding on east elevation and building podium balconies; Building F continuing with metal cladding and installing aluminum cladding to box projections. For internal fit out: Building A continuing gib stopping to apartments and work on bathrooms, started trim and painting; Building B continuing painting to apartments and work on bathrooms, started installing kitchens; Building C and Building D taking CCC inspections with Council、NZRG and Context architects; Building E continuing with second fix services and carpet in Type E apartments, laying carpet in Type H apartments, tiling kitchens in Type F apartments, and working in hallways; Building F completed second fix services and carpet in Type B apartments, working on second fix services and carpet in Type G apartments, and working in hallways; For road & landscaping, continuing with kerbing, footpaths, timber edging, garden beds and limechip, working on drainage and treepits, watermain connection done by Watercare.

IMG_8010
IMG_8693
IMG_8278
IMG_8264
IMG_8252
IMG_8667

  • Construction Progress
    August 2017



  • For external façade: Building A and Building B continuing with designer series, and installing glass to balustrades; Building C continuing on balcony and completed shopfront aluminium joinery; Building D completed metal cladding and plastering; Building E continuing with metal cladding; Building F continuing with metal cladding and aluminum cladding to box projections. For internal fit out: Building A and Building B continuing gib fixing and stopping to apartments, and work on bathrooms; Building C and Building D taking CCC inspections with council; Building E started tiling kitchens in Type E apartments, installing kitchens in Type H apartments and painting in Type F apartments; Building F started tiling kitchens in Type B apartments and installing kitchens in Type G apartments. For road & landscaping, continuing with kerbing, footpaths, timber edging, garden beds and limechip, will start install cabling for streetlighting soon.

IMG_4246
IMG_4248
IMG_4249
IMG_4250
IMG_4251
IMG_4253
IMG_4254

  • Construction Progress
    July 2017



  • For external façade: Building A and Building B continuing with designer series; Building C constructing lobby roof and completing balcony; Building D almost complete metal cladding and plastering in progress; Building E working on level one eyebrows; Building F completed remaining windows and glazing effected by box projections. For internal fit out: Building A and Building B continuing gib fixing and stopping to apartments, and work in bathrooms; Building C and Building D finishing off cleaning and various remedials; Building E continuing with gib fixing and bathrooms in all apartments, installing kitchens to Type E apartments and started painting in Type H apartments; Building F started painting in type B apartments, and tiling to bathrooms. For road & landscaping, continuing with kerbing, footpaths, timber edging, garden beds and limechip. Working on vehicle crossing off Don Mckinnon Drive.

6
0705_1
0705_2
2
1
3

  • Construction Progress
    June 2017



  • For external façade: Building A and Building B installing windows and glazing on east elevation (Rose Garden Lane side); Building C installing metal cladding; Building D completed, and all scaffold tripped (except for metal cladding area); Building E continuing with designer series; Building F received details to complete last of aluminum joinery and glazing on north elevation (Don McKinnon Drive side). For internal fit out: Building A is waiting for facade; Building B started gib fixing to IT walls and bathrooms; Building C & Building D finishing off cleaning and working in stairs in basement; Building E continuing with gib fixing in all apartments, commenced tiling to bathroom floors and walls, started stopping to Type E and H apartments; Building F started stopping in type B apartments, and started tiling to bathrooms. For road & landscaping, completed walls and steps in reserve, and poured kerbing.

IMG_3814
IMG_3793
IMG_3815
IMG_3794
IMG_3809
IMG_3797
IMG_3798

  • Construction Progress
    May 2017



  • For external façade: Building A and Building B continuing on RAB and started on window flashings on east elevation (Rose Garden Lane side); Building C continuing with stripping scaffold on east elevation (Rose Garden Lane side), completing installing designer series on west elevation (podium side), installed wrap and battens for metal cladding. Building D completed, and all scaffold tripped (except for metal cladding area). Still resolving metal cladding details around window openings – currently working on sample area; Building E continuing on flashing and torch-on membrane on eyebrows,  and installing designer series; Building F completed designer series on south elevation (podium side), and completing last of aluminum joinery and glazing on north elevation (Don McKinnon Drive side). For internal fit out: Building A and B are still waiting for facade; Building C continuing with carpet and second fix services in Type B and D apartments, started carpet and second fix services in Type I apartments, and working in halls & stairs; Building D completed type K apartments, continuing with carpet and second fix services in type E apartments, started carpet and second fix services in type F apartments, and working in halls & stairs; Building E continuing with gib fixing in all apartments, commenced acoustic board and waterproofing to bathroom floors, started installing vanities, and continuing with installing timber stairs; Building F continuing with gib fixing to bathrooms in type B apartments, and started stopping in bathrooms. For road & landscaping, completed treepits, started on concrete bedding over treepits for kerbing. Continuing with walls and steps in reserve, and continuing on footpath area in front of building D.

IMG_3747
IMG_3742
IMG_3736
IMG_3741
IMG_3744
IMG_3745
IMG_3746

  • Construction Progress
    April 2017



  • For external façade: Building A started on taping and installing window flashing on west elevation (podium side), continuing with RAB on east elevation (Rose Garden Lane side); Building B installed aluminum joinery on west elevation (podium side), continuing with RAB on east elevation (Rose Garden Lane side); Building C completed south elevation (lake side), started stripping scaffold, installed wrap and battens for metal cladding, installing designer series, glass for balustrades and louvers on other elevations. Building D completed, and all scaffold tripped (except for metal cladding area), started installing metal cladding; Building E continuing on flashing and torch-on membrane on eyebrows,  installing designer series; Building F installed glazing to aluminum joinery on south elevation (podium side),  continuing with designer series on south elevation (podium side), installing flashing and membrane to balconies, and installing flashing and RAB board to north elevation (Don McKinnon side). For internal fit out: Building A and B are waiting for facade; Building C installed kitchens in type B apartments, and laying tiles to kitchen floor. Also stated second fix services, painting type D apartments, started painting in type I apartments; Building D completed type K apartments. Installed kitchens in type E apartments, and laying tiles to kitchen floor. Also started second fix services, painting in type F apartments, and started installing kitchens; Building E continuing with gib fixing to bathrooms in type E & F apartments; Building F continuing with gib fixing to bathrooms in type B apartments. For road & landscaping, continuing with treepits, walls & steps in reserve, and footpath area in front of building D.

IMG_3582
IMG_3580
IMG_3583
IMG_3584
IMG_3585
IMG_3588
IMG_3586

  • Construction Progress
    March 2017



  • For external façade: Building A and B completed roof framing and ply, roof membrane and wall framing. Continuing with RAB on west elevation (podium side); Building C and D continuing with designer series cladding, installing glass for balustrades & battens for metal cladding; Building E started designer series and continuing on flashings on eyebrows; Building F completed installing aluminum joinery on south elevation (podium side). For internal fit out: Building A and B still have completed steel stud and service first fix on level 6; Building C started painting in type B apartments and gib stopping in type I apartments. Continuing with gib stopping and bathroom vanities & tiling in type D apartments; Building D started painting in type E apartments. Continuing with second fix services in type in K apartments and gib stopping & bathroom vanities & tiling in type F apartments; Building E completed gib stopping in type I apartments. For road & landscaping, continuing with treepits, and walls & steps in reserve.

IMG_3424
IMG_3426
IMG_3427
IMG_3430
IMG_3431
IMG_3432
IMG_3433

  • Construction Progress
    February 2017



  • For external façade: Building A and B still continuing with roof framing and ply, and started wall framing. Building C and D continuing with designer series cladding, the aluminum joinery and glazing are almost completed. Building E and F continuing installing aluminum joinery and RAB board. For internal fit out: Building A and B still continuing with steel stud and service first fix on level 6. Building C and D started gib fixing in apartments, and started installing vanities and some tiling. Building E and F completed steel stud and services first fix.