  • Construction Progress
    May 2017



  • For external façade: Building A and Building B continuing on RAB and started on window flashings on east elevation (Rose Garden Lane side); Building C continuing with stripping scaffold on east elevation (Rose Garden Lane side), completing installing designer series on west elevation (podium side), installed wrap and battens for metal cladding. Building D completed, and all scaffold tripped (except for metal cladding area). Still resolving metal cladding details around window openings – currently working on sample area; Building E continuing on flashing and torch-on membrane on eyebrows,  and installing designer series; Building F completed designer series on south elevation (podium side), and completing last of aluminum joinery and glazing on north elevation (Don McKinnon Drive side). For internal fit out: Building A and B are still waiting for facade; Building C continuing with carpet and second fix services in Type B and D apartments, started carpet and second fix services in Type I apartments, and working in halls & stairs; Building D completed type K apartments, continuing with carpet and second fix services in type E apartments, started carpet and second fix services in type F apartments, and working in halls & stairs; Building E continuing with gib fixing in all apartments, commenced acoustic board and waterproofing to bathroom floors, started installing vanities, and continuing with installing timber stairs; Building F continuing with gib fixing to bathrooms in type B apartments, and started stopping in bathrooms. For road & landscaping, completed treepits, started on concrete bedding over treepits for kerbing. Continuing with walls and steps in reserve, and continuing on footpath area in front of building D.

IMG_3747
IMG_3742
IMG_3736
IMG_3741
IMG_3744
IMG_3745
IMG_3746

  • Construction Progress
    April 2017



  • For external façade: Building A started on taping and installing window flashing on west elevation (podium side), continuing with RAB on east elevation (Rose Garden Lane side); Building B installed aluminum joinery on west elevation (podium side), continuing with RAB on east elevation (Rose Garden Lane side); Building C completed south elevation (lake side), started stripping scaffold, installed wrap and battens for metal cladding, installing designer series, glass for balustrades and louvers on other elevations. Building D completed, and all scaffold tripped (except for metal cladding area), started installing metal cladding; Building E continuing on flashing and torch-on membrane on eyebrows,  installing designer series; Building F installed glazing to aluminum joinery on south elevation (podium side),  continuing with designer series on south elevation (podium side), installing flashing and membrane to balconies, and installing flashing and RAB board to north elevation (Don McKinnon side). For internal fit out: Building A and B are waiting for facade; Building C installed kitchens in type B apartments, and laying tiles to kitchen floor. Also stated second fix services, painting type D apartments, started painting in type I apartments; Building D completed type K apartments. Installed kitchens in type E apartments, and laying tiles to kitchen floor. Also started second fix services, painting in type F apartments, and started installing kitchens; Building E continuing with gib fixing to bathrooms in type E & F apartments; Building F continuing with gib fixing to bathrooms in type B apartments. For road & landscaping, continuing with treepits, walls & steps in reserve, and footpath area in front of building D.

IMG_3582
IMG_3580
IMG_3583
IMG_3584
IMG_3585
IMG_3588
IMG_3586

  • Construction Progress
    March 2017



  • For external façade: Building A and B completed roof framing and ply, roof membrane and wall framing. Continuing with RAB on west elevation (podium side); Building C and D continuing with designer series cladding, installing glass for balustrades & battens for metal cladding; Building E started designer series and continuing on flashings on eyebrows; Building F completed installing aluminum joinery on south elevation (podium side). For internal fit out: Building A and B still have completed steel stud and service first fix on level 6; Building C started painting in type B apartments and gib stopping in type I apartments. Continuing with gib stopping and bathroom vanities & tiling in type D apartments; Building D started painting in type E apartments. Continuing with second fix services in type in K apartments and gib stopping & bathroom vanities & tiling in type F apartments; Building E completed gib stopping in type I apartments. For road & landscaping, continuing with treepits, and walls & steps in reserve.

IMG_3424
IMG_3426
IMG_3427
IMG_3430
IMG_3431
IMG_3432
IMG_3433

  • Construction Progress
    February 2017



  • For external façade: Building A and B still continuing with roof framing and ply, and started wall framing. Building C and D continuing with designer series cladding, the aluminum joinery and glazing are almost completed. Building E and F continuing installing aluminum joinery and RAB board. For internal fit out: Building A and B still continuing with steel stud and service first fix on level 6. Building C and D started gib fixing in apartments, and started installing vanities and some tiling. Building E and F completed steel stud and services first fix.

IMG_3373
IMG_3374
IMG_3370
IMG_3375
IMG_3376
IMG_3377
IMG_3378

  • Construction Progress
    January 2017



  • For external façade, Building A and B continuing with roof framing and ply, and started wall framing. Building C and D continuing with designer series. Building E and F roof membrane done, started installing aluminum joinery. For internal fit out, Building A and B continuing with steel stud and service first fix on level 6. Building C started gib stopping in bathrooms,  and gib fixing in apartments. Building D started painting in apartment, and soundboard、waterproofing to bathrooms, continuing with gib fixing in apartments. Building E and F completed steel stud and services first fix.

img_3177
img_3169
img_3168
img_3171
img_3170
img_3172
img_3176

  • Construction Progress
    December 2016



  • For internal fitout works, building A and B working on steel stud and all services first fix, building C、D、E、F are completed steel stud and most of services first fix. For external façade, building D is continue with closing in building with aluminum joinery installation and glazing, as well as the designer series cladding, building C is continue with RAB and aluminum joinery installation. Other buildings are ready to start with designer series and glazing installation.

rosegarden
img_2835
img_2834
img_2836
img_2841
img_2842
rosegarden_o

  • Construction Progress
    November 2016



  • The structural works for all buildings are completed, and roof works are in progress to make the buildings watertight. The internal fitouts、services first fix、gib fixing、RAB、aluminum joinery installation for each building are continue in progress.

img_2575
img_2577
img_2578
img_2579
img_2580
img_2582

  • Construction Progress
    October 2016



  • The structural works for all buildings have reached the top floor, and roof works are in progress to make the buildings watertight. The internal fit out works and wall framing for each building are continue in progress.

img_2208
img_2222
img_2215
img_2221
img_2216
img_2214
img_2219

  • Construction Progress
    September 2016



  • The structural works for Building A & Building B are working on level 5, Building E & Building F have reached the top floor. Building C & Building D roof structure are installed and roof works are in progress to make the buildings watertight, which will allow the internal fit out works to commence. The installation of internal wall framing for each building and lift installation are continue in progress.

DCIM100MEDIADJI_0116.JPG
IMG_1848
IMG_1851
IMG_1850
IMG_1856
IMG_1858

  • Construction Progress
    August 2016



  • The structural works for Building A level 3 and Building B level 4 are completed. Building C、Building E and Building F have reached to level 5、level 6 and level 6 respectively. Building D level 6 work on roof has almost completed. The installation of the services have already completed from the Basements and Podiums, and the installation of internal wall framing for each building are in progress.